The government finally agreed a nuclear strike price with French power company EDF in 2013. But what is this price and why is it needed?

nuclear map
Hinkley Point C
Hinkley Point C is set to take 10 years to become fully operational. It will be made up of two nuclear reactors and will be built next to Hinkley Point A and B. HayesDavidson
Sea wall at Hinkley Point C
The land will need to be flattened and then the sea wall will be built. After this, excavation work can start to lay the foundations of the nuclear plant including two underground two-mile (3km) tunnels for the cooling water. HayesDavidson
Turbine hall
The building of the two reactors will be staggered with the first reactor expected to be operational by 2023. EDF Energy
Turbine hall
The other aspects of the build include the turbine halls, standby power generators and a pumping station for the cooling water, interim waste storage facilities as well as a visitors' centre. Geoff Pagotto
Workers' campus (artist impression)
Workers' accommodation will be built across three sites, with two in Bridgwater and a third on site. Other infrastructure includes building two park and ride sites and developing Combwich Wharf. other
View of Hinkley Point C with Hinkley Point A and B in the background
The power station is expected to provide up to 25,000 jobs during the lifetime of the project and once built will provide about 900 full-time jobs. EDF Energy