When can I board a tram in Dudley?

A blue tram snakes through the town with Dudley Castle visible in the background. Workmen in orange gear can be seen to the right monitoring the tram. The sun is shining.
The first tram tests in Dudley town centre were carried out in June TfWM

Trams are being tested on the new Dudley extension of the West Midlands Metro network as the long-awaited scheme that has been beset with delays comes to fruition.

Over the next few weeks, trams will become an increasingly common sight along the line between Wednesbury and Dudley, transport bosses said, as part of driver training.

Pedestrians and drivers are being advised by West Midlands Metro to look out for the trams on the new route as tests continue.

It is now expected that passenger services will begin in early 2027.

Where will the trams run?

Two drivers sit in the front cab of a tram as it is tested in Dudley. They are wearing orange work gear and look out at the track ahead.
Driver training was now under way on the new route, TfWM said on Tuesday TfWM

The new route branches off the Metro line which runs between Birmingham and Wolverhampton at the Wednesbury Great Western Metro stop.

Heading through Tipton, it will travel into Dudley over Birmingham New Road and past the castle to the town centre.

There will be nine new stops from Wednesbury to Flood Street. The timetable is yet to be finalised, Transport for West Midlands (TfWM) said.

It is the first phase of the scheme which will take the Metro to Brierley Hill. A second phase will see it be expanded to Merry Hill Shopping Centre.

The project is being delivered by the Midland Metro Alliance on behalf of the West Midlands Combined Authority and Transport for West Midlands.

Why has the service been delayed?

A man wearing a white shirt and black blazer with short grey hair looks at the camera. Behind him are grey metal fences on a train platform.
Dudley council leader Patrick Harley has let his feelings be known about the delays to get trams operational in Dudley BBC

The link from Wednesbury was scheduled to open in August this year, and was already two years late.

The delays have been blamed on increasing costs and unexpected extra work, which only came to light during construction.

The issues have prompted much frustration and anger from Dudley's Conservative council leader Patrick Harley as well as traders complaining about the impact of the work on their struggling businesses.

He called for sackings in June when the authority was told the August opening deadline would be missed.

TfWM said at the time there had been "adverse movement" to the timescale after delays with signal commissioning.

It has described the scheme as "a complex engineering project" involving more than four miles of track, signalling, junctions and electrical systems, adding that only through extensive testing of individual systems can issues be identified and resolved.

Announcing passenger services would now begin in early 2027, TfWM said earlier this month, "a safety-critical issue was identified during testing and required additional engineering work before the extension could be approved for passenger service.

"Resolving this issue took longer than anticipated and has affected the project timetable."

At the same time, West Midlands Mayor Richard Parker, said that "the people of Dudley have been badly let down by the repeated delays".

Parker, who came to office in 2024, spoke as his review of the delivery of the Metro ↗ was submitted to the WMCA board, and said what happened must be investigated to prevent similar delays from happening again.

Where will the next extension be?

A map, released before work was completed, shows what routes are in operation, marked in blue and spreading from Wolverhampton, Birmingham and Edgbaston. Routes under construction are marked in pink spanning out to Merry Hill and into Digbeth. Further routes in development, out to Birmingham Airport and Brierley Hill.
This map shows the now completed Dudley route in pink and the plans to extend to Merry Hill Midland Metro Alliance

The second phase of the tram extension will see the network reaching Merry Hill Shopping Centre, in Brierley Hill.

Work started at the centre in spring 2025 with trams expected to start taking passengers in 2028, TfWM said.

Phase two will include five stops between Flood Street in Dudley and Brierley Hill, with provision for one additional stop.

The third phase to Brierley Hill town centre is still being planned with funding yet to be secured.

What are the costs?

A tram passes by Dudley Zoo. A worker in orange gear walks to the right of it by the zoo entrance.
Pedestrians are reminded to use designated crossing points and remember that trams cannot swerve and take longer to stop than other road vehicles, TfWM said TfWM

The budget for the first phase from Wednesbury to Dudley is £393m, which was agreed by the West Midlands Combined Authority (WMCA) board in July 2024, TfWM said.

The cost of bringing trams to Brierley Hill has received government funding after rising costs.

In 2023, the Express and Star newspaper reported the cost of linking Wednesbury to Brierley Hill ↗ had increased by 45%, from £449m to £650m.

In October 2024, then chancellor Rachel Reeves committed extra funding to the project in her October budget as part of an announcement to spend £1.3bn on several transport schemes.

Speaking at the time, West Midlands Mayor Richard Parker said it was "a very important announcement" as there had been "no money to complete that line in the past despite all the announcements".

Midland Metro Alliance and WMCA have said the extension will attract investment and regeneration to Sandwell and Dudley, improve public transport accessibility across the Black Country, reducing journey times as well as improving air quality.