Chain ferry refit schedule delayed by weather

Cars and vans pack the deck of Sandbanks Ferry as it crosses the mouth of Poole Harbour. The vessel is white with a single ground-level car deck and two raised passenger decks either side.
Sandbanks Ferry helps motorists avoid a road journey of up to 25 miles (40km) David Martin

A major refit on a chain ferry has been delayed by a week due to the weather.

The Sandbanks Ferry, which crosses the entrance to Poole Harbour, closed for scheduled maintenance at the start of November.

The works were expected to take seven weeks but rain in Falmouth, where the refit took place, delayed the paint works, and adverse sea conditions meant tugs had to wait for a weather window before towing the vessel back to Poole.

Bournemouth Swanage Motor Road and Ferry Company said it hoped to accelerate the remaining works and get the ferry back in service before Christmas.

Maintenance work on the ferry is carried out every two years, alternating between major and minor refits. Its last major overhaul took place in 2022.

The Sandbanks Ferry takes about four minutes to cross Poole Harbour and helps motorists avoid a road journey of up to 25 miles (40km).

Ferry workers close the gates to the open-deck, roll-on roll-off, chain ferry at sunset, as it prepares to cross the entrance to Poole Harbour.
Operators hope to return the ferry to service before Christmas Malc McDonald

In an update, the firm said: "We're pleased to share that Bramble Bush Bay is en route back to Poole after undergoing refit works in Falmouth.

"Due to adverse sea conditions, our tow back to Poole was delayed as we've had to wait for an appropriate weather window to tow safely.

"The persistent rain in Falmouth has also caused a delay to our paint works, which we'll now be completing in Poole.

"This means our refit schedule has been pushed back by approximately seven days.

"However, our team is working incredibly hard to accelerate works and get Bramble Bush Bay back up and running this side of Christmas."