Council unable to confirm when storm-hit leisure centre will reopen
Council bosses have yet to confirm when Helensburgh Leisure Centre will reopen, almost two years after it was closed in the wake of damage sustained during Storm Eowyn.
The seaside town's community council expressed concern at the pace of progress, despite the fact a recent works update confirmed that the roof repairs had been completed.
The facility has been closed since parts of its roof were ripped off in January last year.
A report by Councillor Ross Moreland, the local authority's policy lead for finance and commercial services, featured photos showing bare walls and other damage inside the centre.
Community council convener Dr Peter Brown asked: "Now that the roof has been completed, can the committee confirm what remains preventing the reopening of the leisure centre?
"And will the council publish a detailed public timetable showing the remaining works and milestones leading to the reopening?"
A council official said this was not possible.
The meeting also heard a response from an official in estates, who said reopening the centre, particularly the swimming pool, remained a priority.
He added: "The permanent roof replacement is now complete, however an internal strip-out has identified a number of potential defects requiring further assessment and survey work before the full scope of repairs can be finalised with the relevant parties.
"We are therefore not in a position to provide a definitive reopening timescale, but will do so as soon as a programme is developed.
"Formal legal notices have been issued and while these proceedings are ongoing, it would not be in the best interests to comment substantially."
Councillor Maurice Corry said reopening the pool was desperately needed in the area, and he received questions on it every day.
Story by Local Democracy Reporting Service reporter Andrew Galloway.